Action Date | Action Description |
---|---|
Sep 24, 2004 | Application Accepted |
Nov 01, 2004 | Historical Preservation Approval Granted |
Dec 01, 2004 | Biologist Report |
Dec 01, 2004 | Engineering Report |
Dec 07, 2004 | Permit Approved |
Dec 07, 2004 | Land Evidence Date |
Sep 24, 2007 | Extension of Permit Request |
Oct 03, 2007 | Enforcement Compliance Inspection Required |
Oct 09, 2007 | Process Extension |
Oct 09, 2007 | Typist for Processing |
Oct 09, 2007 | Executive Sign Off |
Oct 09, 2007 | Sent to Photo Copy |
Oct 09, 2007 | Extension Approved |
Oct 03, 2008 | Extension of Permit Request |
Oct 16, 2009 | Correspondence Mailed/Faxed/E-mailed |
Oct 19, 2009 | Enforcement Compliance Inspection Required |
Oct 21, 2009 | Process Extension |
Oct 21, 2009 | Extension Approved |
Dec 22, 2010 | Extension of Permit Request |
Feb 25, 2011 | Extension Toll letter mailed |