Action Date | Action Description |
---|---|
Feb 16, 2005 | Assent Application Received |
Feb 17, 2005 | Administrative Review for Completeness |
Mar 02, 2005 | Deficient Application - Owner Notification Sent |
May 27, 2005 | Deficiency Response Received |
Jun 16, 2005 | Deficient Application - Owner Notification Sent |
Aug 01, 2005 | Deficiency Response Received |
Aug 29, 2005 | Team Review for Completeness |
Aug 29, 2005 | Application Accepted |
Aug 29, 2005 | Category A* (Docks) |
Sep 06, 2005 | HPHC Review Pending |
Oct 12, 2005 | 30 day Public Notice Issued |
Nov 12, 2005 | Public Notice End Date |
Nov 16, 2005 | US Army Corp of Engineers Permit Date |
Nov 21, 2005 | US Army Corps of Engineers Approval Received |
Nov 22, 2005 | Biologist Report |
Jan 27, 2006 | Dock sub-committee Approved |
Jan 27, 2006 | Engineering Report |
Feb 03, 2006 | Typist for Processing |
Feb 03, 2006 | Executive Sign Off |
Feb 03, 2006 | Sent to Photo Copy |
Feb 03, 2006 | Permit Approved |
May 02, 2006 | Land Evidence Date |
Jan 21, 2009 | Extension of Permit Request |
Jan 22, 2009 | Enforcement Compliance Inspection Required |
Jan 23, 2009 | Process Extension |
Jan 23, 2009 | Extension Approved |
Dec 19, 2012 | Extension Toll letter mailed |
Jan 28, 2013 | US Army Corps of Engineers Approval Received |
Jun 11, 2013 | Extension Toll letter mailed |