Action Date | Action Description |
---|---|
Feb 24, 2005 | Assent Application Received |
Feb 25, 2005 | Administrative Review for Completeness |
Mar 01, 2005 | Team Review for Completeness |
Mar 01, 2005 | Application Accepted |
Mar 15, 2005 | Engineering Report |
Mar 15, 2005 | Typist for Processing |
Mar 15, 2005 | Permit Approved |
Mar 16, 2005 | HPHC Review Pending |
Mar 17, 2005 | Executive Sign Off |
Mar 17, 2005 | Sent to Photo Copy |
Mar 23, 2005 | Land Evidence Date |