Action Date | Action Description |
---|---|
Mar 21, 2005 | Assent Application Received |
Mar 22, 2005 | Administrative Review for Completeness |
Mar 22, 2005 | Team Review for Completeness |
Mar 22, 2005 | Application Accepted |
Apr 01, 2005 | Additional Information Requested from Applicant |
Apr 15, 2005 | Biologist Report |
Apr 15, 2005 | Engineering Report |
Apr 18, 2005 | Typist for Processing |
Apr 18, 2005 | Executive Sign Off |
Apr 18, 2005 | Sent to Photo Copy |
Apr 18, 2005 | Permit Approved |
Apr 19, 2005 | Historical Preservation Approval Granted |
Apr 19, 2005 | HPHC Review Pending |
Apr 25, 2005 | Commencement of Work Notice received |
Apr 26, 2005 | Land Evidence Date |