Action Date | Action Description |
---|---|
Apr 06, 2005 | Assent Application Received |
Apr 07, 2005 | Administrative Review for Completeness |
May 12, 2005 | Team Review for Completeness |
May 12, 2005 | Application Accepted |
May 12, 2005 | 30 day Public Notice Issued |
May 12, 2005 | Category B assigned |
May 26, 2005 | Historical Preservation Approval Granted |
May 27, 2005 | HPHC Review Pending |
Jun 12, 2005 | Public Notice End Date |
Jun 16, 2005 | US Army Corp of Engineers Permit Date |
Jun 20, 2005 | US Army Corps of Engineers Approval Received |
Jun 27, 2005 | Additional Information Received |
Jul 28, 2005 | Biologist Report |
Jul 29, 2005 | Engineering Report |
Aug 01, 2005 | Supervisor Biologist SignOff |
Aug 01, 2005 | Executive Sign Off |
Aug 18, 2005 | Ready to Schedule Semi-Monthly Meeting |
Aug 18, 2005 | Mail Agenda Notice |
Aug 23, 2005 | Semi-Monthly Meeting Date Scheduled |
Aug 23, 2005 | Semi-Monthly Meeting Held |
Aug 23, 2005 | Council Approval Granted |
Aug 30, 2005 | Stipulation Package from Biologist |
Aug 30, 2005 | Stipulation Package by Engineer |
Aug 31, 2005 | Executive Sign Off |
Aug 31, 2005 | Sent to Photo Copy |
Aug 31, 2005 | Permit Approved |
Aug 31, 2005 | Typist for Processing |
Oct 21, 2005 | Land Evidence Date |
Nov 15, 2005 | Legal Response/Decision |
Nov 29, 2005 | Under Review/Decision |