Action Date | Action Description |
---|---|
Jun 06, 2005 | Assent Application Received |
Jun 07, 2005 | Administrative Review for Completeness |
Jun 14, 2005 | Team Review for Completeness |
Jun 14, 2005 | Application Accepted |
Jul 15, 2005 | HPHC Review Pending |
Sep 13, 2005 | Engineering Report |
Sep 13, 2005 | Typist for Processing |
Sep 13, 2005 | Executive Sign Off |
Sep 13, 2005 | Sent to Photo Copy |
Sep 13, 2005 | Permit Approved |
Sep 23, 2005 | Land Evidence Date |
Mar 30, 2007 | Maintenance/Repair/Location within the Marina Perimeter |
Mar 30, 2007 | Engineering Report |
Feb 13, 2013 | Modification Request |
Feb 15, 2013 | Administrative Review for Completeness |
Apr 05, 2013 | Team Review for Completeness |
May 02, 2013 | 30 day Public Notice Issued |
May 06, 2013 | HPHC Historical Preservation No Effect |
Jun 02, 2013 | Public Notice End Date |
Sep 05, 2013 | Engineering Report |
Oct 22, 2013 | Executive Signoff of Staff Reports |
Nov 13, 2013 | Ready to Schedule Semi-Monthly Meeting |
Nov 13, 2013 | Mail Agenda Notice |
Nov 26, 2013 | Semi-Monthly Meeting Held |
Nov 26, 2013 | Council Approval Granted |
Nov 26, 2013 | Semi-Monthly Meeting Date Scheduled |
Nov 27, 2013 | Legal Response/Decision |
Dec 03, 2013 | 30 Day Appeal Notification to Owner |
Apr 11, 2014 | Modification Approved |
Apr 11, 2014 | Stipulation Package by Engineer |
Aug 19, 2014 | Duplicate Original Assent requested/mailed |
Sep 02, 2014 | Phone Call |
Sep 03, 2014 | Duplicate Original Assent requested/mailed |
Sep 09, 2014 | Land Evidence Date |
Jan 14, 2016 | Maintenance/Repair/Location within the Marina Perimeter |
Apr 18, 2018 | Maintenance/Repair/Location within the Marina Perimeter |
May 17, 2023 | Maintenance/Repair/Location within the Marina Perimeter |