Action Date | Action Description |
---|---|
Aug 09, 2005 | Maintenance Certification Request |
Aug 10, 2005 | Administrative Review for Completeness |
Aug 11, 2005 | Deficient Application - Owner Notification Sent |
Oct 14, 2005 | Deficiency Response Received |
Oct 17, 2005 | Team Review for Completeness |
Oct 17, 2005 | Application Accepted |
Oct 18, 2005 | Engineering Report |
Oct 18, 2005 | Biologist Report |
Oct 19, 2005 | Typist for Processing |
Oct 19, 2005 | Executive Sign Off |
Oct 19, 2005 | Sent to Photo Copy |
Oct 19, 2005 | Permit Approved |
Oct 25, 2005 | HPHC Historical Preservation No Effect |