Action Date | Action Description |
---|---|
Aug 11, 2005 | Assent Application Received |
Aug 12, 2005 | Administrative Review for Completeness |
Aug 12, 2005 | Category A* (Docks) |
Aug 19, 2005 | Deficient Application - Owner Notification Sent |
Aug 25, 2005 | Deficient Application Picked Up |
Sep 06, 2005 | Deficiency Response Received |
Sep 09, 2005 | Team Review for Completeness |
Sep 09, 2005 | Application Accepted |
Sep 30, 2005 | HPHC Review Pending |
Oct 05, 2005 | 30 day Public Notice Issued |
Oct 26, 2005 | Dock Meeting Scheduled (Admin) |
Oct 28, 2005 | Dock sub-committee Approved |
Nov 05, 2005 | Public Notice End Date |
Nov 16, 2005 | Typist for Processing |
Nov 16, 2005 | Executive Sign Off |
Nov 16, 2005 | Sent to Photo Copy |
Nov 16, 2005 | Permit Approved |
Nov 16, 2005 | Engineering Report |
Nov 16, 2005 | Biologist Report |
Nov 28, 2005 | US Army Corp of Engineers Permit Date |
Nov 30, 2005 | US Army Corps of Engineers Approval Received |
Jan 17, 2006 | Land Evidence Date |