Action Date | Action Description |
---|---|
Legal Response/Decision | |
Sep 12, 2005 | Correspondence Received |
Sep 21, 2005 | Assent Application Received |
Sep 22, 2005 | Administrative Review for Completeness |
Oct 03, 2005 | Team Review for Completeness |
Oct 03, 2005 | Application Accepted |
Oct 03, 2005 | Category B assigned |
Oct 18, 2005 | 30 day Public Notice Issued |
Oct 18, 2005 | 30 day Public Notice Issued |
Oct 31, 2005 | US Army Corp of Engineers Permit Date |
Nov 09, 2005 | US Army Corps of Engineers Approval Received |
Nov 17, 2005 | Correspondence Received |
Nov 18, 2005 | Public Notice End Date |
Nov 18, 2005 | Public Notice End Date |
Dec 06, 2005 | Water Quality Certification |
Dec 06, 2005 | Correspondence Received |
Dec 16, 2005 | Water Quality Certification |
Jan 24, 2006 | Biologist Report |
Jan 24, 2006 | Engineering Report |
Jan 27, 2006 | Supervisor Engineer SignOff |
Jan 27, 2006 | Supervisor Biologist SignOff |
Jan 27, 2006 | Executive Sign Off |
Feb 07, 2006 | Ready to Schedule Semi-Monthly Meeting |
Feb 07, 2006 | Mail Agenda Notice |
Feb 14, 2006 | Semi-Monthly Meeting Held |
Feb 14, 2006 | Council Approval Granted |
Feb 14, 2006 | Semi-Monthly Meeting Date Scheduled |
Feb 28, 2006 | Stipulation Package from Biologist |
Feb 28, 2006 | Stipulation Package by Engineer |
Feb 28, 2006 | Typist for Processing |
Feb 28, 2006 | Executive Sign Off |
Feb 28, 2006 | Sent to Photo Copy |
Feb 28, 2006 | Permit Approved |