Action Date | Action Description |
---|---|
Nov 01, 2005 | Assent Application Received |
Nov 02, 2005 | Administrative Review for Completeness |
Nov 07, 2005 | Team Review for Completeness |
Nov 07, 2005 | Application Accepted |
Nov 07, 2005 | Category A* (Docks) |
Nov 16, 2005 | 30 day Public Notice Issued |
Nov 29, 2005 | HPHC Historical Preservation No Effect |
Dec 16, 2005 | Public Notice End Date |
Jan 11, 2006 | Biologist Report |
Jan 18, 2006 | US Army Corp of Engineers Permit Date |
Jan 20, 2006 | US Army Corps of Engineers Approval Received |
Jan 27, 2006 | Dock sub-committee Approved |
Jan 27, 2006 | Engineering Report |
Feb 03, 2006 | Permit Approved |
Feb 03, 2006 | Typist for Processing |
Feb 03, 2006 | Executive Sign Off |
Feb 03, 2006 | Sent to Photo Copy |
Feb 09, 2006 | Land Evidence Date |
Oct 16, 2006 | Commencement of Work Notice received |