Action Date | Action Description |
---|---|
May 30, 2006 | Assent Application Received |
May 30, 2006 | Administrative Review for Completeness |
Jun 02, 2006 | Team Review for Completeness |
Jun 02, 2006 | Application Accepted |
Jun 21, 2006 | HPHC Historical Preservation No Effect |
Aug 02, 2006 | Plans Received |
Aug 22, 2006 | Plans Received |
Aug 30, 2006 | Biologist Report |
Aug 30, 2006 | Engineering Report |
Aug 31, 2006 | Typist for Processing |
Aug 31, 2006 | Executive Sign Off |
Aug 31, 2006 | Sent to Photo Copy |
Aug 31, 2006 | Permit Approved |
Sep 01, 2006 | Land Evidence Date |
Oct 12, 2006 | Modification Request |
Oct 13, 2006 | Administrative Review for Completeness |
Oct 18, 2006 | Team Review for Completeness |
Nov 01, 2006 | HPHC Historical Preservation No Effect |
Nov 30, 2006 | Biologist Report |
Nov 30, 2006 | Engineering Report |
Dec 01, 2006 | Typist for Processing |
Dec 01, 2006 | Executive Sign Off |
Dec 01, 2006 | Sent to Photo Copy |
Dec 01, 2006 | Modification Approved |
Dec 05, 2006 | Land Evidence Date |