Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Jun 21, 2006 | Assent Application Received |
Jun 22, 2006 | Administrative Review for Completeness |
Aug 21, 2006 | Deficiency Response Received |
Aug 21, 2006 | Additional Information Received |
Aug 31, 2006 | Application Accepted |
Aug 31, 2006 | Team Review for Completeness |
Aug 31, 2006 | Category A* (Docks) |
Aug 31, 2006 | Site Inspection |
Sep 13, 2006 | HPHC Historical Preservation No Effect |
Sep 27, 2006 | 30 day Public Notice Issued |
Oct 27, 2006 | Public Notice End Date |
Oct 27, 2006 | Dock Meeting Scheduled (Admin) |
Nov 16, 2006 | Engineering Report |
Nov 16, 2006 | Biologist Report |
Nov 17, 2006 | Permit Approved |
Nov 17, 2006 | Typist for Processing |
Nov 17, 2006 | Executive Sign Off |
Nov 17, 2006 | Sent to Photo Copy |
Nov 21, 2006 | US Army Corp of Engineers Permit Date |
Nov 27, 2006 | US Army Corps of Engineers Approval Received |
Feb 20, 2007 | Land Evidence Date |
Dec 06, 2016 | Modification Request |
Dec 07, 2016 | Administrative Review for Completeness |
Dec 13, 2016 | Team Review for Completeness |
Dec 13, 2016 | Application Accepted |
Feb 10, 2017 | 30 day Public Notice Issued |
Mar 06, 2017 | HPHC Historical Preservation No Effect |
Mar 10, 2017 | Public Notice End Date |
Mar 20, 2017 | Dock/1.1.6 Review approval |
Mar 23, 2017 | Biologist Report |
Mar 23, 2017 | Typist for Processing |
Mar 23, 2017 | Executive Sign Off |
Mar 23, 2017 | Sent to Photo Copy |
Mar 23, 2017 | Modification Approved |