Action Date | Action Description |
---|---|
Jul 20, 2006 | Assent Application Received |
Jul 21, 2006 | Administrative Review for Completeness |
Jul 24, 2006 | Team Review for Completeness |
Jul 24, 2006 | Application Accepted |
Aug 03, 2006 | HPHC Historical Preservation No Effect |
Aug 04, 2006 | Plans Received |
Oct 11, 2006 | Typist for Processing |
Oct 11, 2006 | Executive Sign Off |
Oct 11, 2006 | Sent to Photo Copy |
Oct 11, 2006 | Permit Approved |
Oct 11, 2006 | Biologist Report |
Oct 11, 2006 | Engineering Report |
Oct 27, 2006 | Land Evidence Date |
Jan 23, 2007 | Commencement of Work Notice received |
Dec 13, 2007 | Modification Request |
Dec 14, 2007 | Administrative Review for Completeness |
Dec 20, 2007 | Team Review for Completeness |
Dec 20, 2007 | Team Review for Completeness |
Jan 07, 2008 | HPHC Historical Preservation No Effect |
Apr 01, 2008 | Typist for Processing |
Apr 01, 2008 | Executive Sign Off |
Apr 01, 2008 | Sent to Photo Copy |
Apr 01, 2008 | Modification Approved |
Apr 01, 2008 | Biologist Report |
Apr 01, 2008 | Engineering Report |
Apr 28, 2008 | Land Evidence Date |