Action Date | Action Description |
---|---|
Aug 02, 2006 | Assent Application Received |
Aug 04, 2006 | Administrative Review for Completeness |
Aug 07, 2006 | Team Review for Completeness |
Aug 07, 2006 | Application Accepted |
Aug 07, 2006 | Category A* (Docks) |
Aug 25, 2006 | HPHC Historical Preservation No Effect |
Aug 30, 2006 | 30 day Public Notice Issued |
Sep 28, 2006 | Objections/Comments Received |
Sep 30, 2006 | Public Notice End Date |
Oct 30, 2006 | US Army Corp of Engineers Permit Date |
Nov 03, 2006 | US Army Corps of Engineers Approval Received |
Feb 26, 2007 | Correspondence Received |
Jul 05, 2007 | Biologist Report |
Jul 05, 2007 | Engineering Report |
Jul 06, 2007 | Typist for Processing |
Jul 06, 2007 | Executive Sign Off |
Jul 06, 2007 | Sent to Photo Copy |
Jul 06, 2007 | Permit Approved |
Jul 13, 2007 | Land Evidence Date |