Action Date | Action Description |
---|---|
Aug 03, 2006 | Freshwater Wetland - Preliminary Determination |
Aug 21, 2006 | Administrative Review for Completeness |
Aug 21, 2006 | Team Review for Completeness |
Aug 21, 2006 | Application Accepted |
Sep 05, 2006 | HPHC Historical Preservation No Effect |
Oct 12, 2006 | Typist for Processing |
Oct 12, 2006 | Executive Sign Off |
Oct 12, 2006 | Sent to Photo Copy |
Oct 12, 2006 | Permit Approved |
Oct 12, 2006 | Biologist Report |
Nov 16, 2006 | Land Evidence Date |
Nov 13, 2007 | Modification Request |
Nov 14, 2007 | Administrative Review for Completeness |
Nov 15, 2007 | Team Review for Completeness |
Nov 24, 2007 | HPHC Historical Preservation No Effect |
Feb 12, 2008 | Plans Received |
Feb 14, 2008 | Biologist Report |
Feb 15, 2008 | Typist for Processing |
Feb 15, 2008 | Executive Sign Off |
Feb 15, 2008 | Sent to Photo Copy |
Feb 15, 2008 | Modification Approved |
Feb 29, 2008 | Land Evidence Date |
Oct 01, 2009 | Extension of Permit Request |
Oct 21, 2009 | Enforcement Compliance Inspection Required |
Oct 21, 2009 | Process Extension |
Jul 16, 2014 | Extension Toll letter mailed |
Jun 20, 2016 | Extension Toll letter mailed |