Action Date | Action Description |
---|---|
Sep 14, 2006 | Assent Application Received |
Sep 15, 2006 | Administrative Review for Completeness |
Sep 18, 2006 | Team Review for Completeness |
Sep 18, 2006 | Application Accepted |
Sep 18, 2006 | Category A* (Docks) |
Sep 28, 2006 | HPHC Historical Preservation No Effect |
Oct 02, 2006 | Joint Public Notice |
Nov 02, 2006 | Public Notice End Date |
Nov 03, 2006 | Objections/Comments Received |
Nov 06, 2006 | Objections/Comments Received |
Nov 27, 2006 | US Army Corp of Engineers Permit Date |
Dec 04, 2006 | US Army Corps of Engineers Approval Received |
Mar 12, 2007 | Engineering Report |
Mar 12, 2007 | Biologist Report |
Mar 13, 2007 | Supervisor Biologist SignOff |
Mar 14, 2007 | Supervisor Engineer SignOff |
Mar 16, 2007 | Executive Sign Off |
Apr 16, 2007 | Ready to Schedule Semi-Monthly Meeting |
Apr 16, 2007 | Mail Agenda Notice |
Apr 24, 2007 | Semi-Monthly Meeting Held |
Apr 24, 2007 | Council Approval Granted |
Apr 24, 2007 | Semi-Monthly Meeting Date Scheduled |
Jun 11, 2007 | Stipulation Package from Biologist |
Jun 11, 2007 | Stipulation Package by Engineer |
Jun 11, 2007 | Permit Approved |
Jun 11, 2007 | Typist for Processing |
Jun 11, 2007 | Executive Sign Off |
Jun 11, 2007 | Sent to Photo Copy |
Jun 27, 2007 | Land Evidence Date |
Jun 26, 2013 | Legal Response/Decision |