Action Date | Action Description |
---|---|
Oct 12, 2006 | Assent Application Received |
Oct 13, 2006 | Administrative Review for Completeness |
Oct 27, 2006 | Team Review for Completeness |
Oct 27, 2006 | Application Accepted |
Nov 02, 2006 | 30 day Public Notice Issued |
Nov 09, 2006 | HPHC Historical Preservation No Effect |
Nov 30, 2006 | Correspondence Received |
Nov 30, 2006 | Correspondence Received |
Dec 02, 2006 | Public Notice End Date |
Jan 18, 2007 | Engineering Report |
Jan 18, 2007 | Geologist Report |
Jan 29, 2007 | Executive Sign Off |
Feb 05, 2007 | Scheduled for Section 110 Review meeting |
Feb 07, 2007 | Dock/1.1.6 Review approval |
Feb 19, 2007 | Executive Sign Off |
Feb 19, 2007 | Sent to Photo Copy |
Feb 19, 2007 | Permit Approved |
Feb 19, 2007 | Typist for Processing |
Feb 20, 2007 | Land Evidence Date |
Mar 16, 2007 | Commencement of Work Notice received |