Action Date | Action Description |
---|---|
Feb 21, 2007 | Dredge Application |
Feb 21, 2007 | Administrative Review for Completeness |
Feb 26, 2007 | Team Review for Completeness |
Feb 26, 2007 | Application Accepted |
Mar 14, 2007 | HPHC Historical Preservation No Effect |
Sep 12, 2007 | Note to File |
Mar 17, 2009 | Plans Received |
May 05, 2009 | Additional Information Received |
May 13, 2009 | Joint Public Notice |
May 18, 2009 | Joint Public Notice |
Jun 03, 2009 | Correspondence Received |
Jun 08, 2009 | Correspondence Received |
Jun 13, 2009 | Public Notice End Date |
Jun 15, 2009 | Engineering Report |
Jun 17, 2009 | Biologist Report |
Jun 18, 2009 | Public Notice End Date |
Jun 25, 2009 | Executive Signoff of Staff Reports |
Jun 30, 2009 | Mail Agenda Notice |
Jul 13, 2009 | Council Approval Granted |
Jul 13, 2009 | Semi-Monthly Meeting Date Scheduled |
Jul 13, 2009 | Semi-Monthly Meeting Held |
Jul 15, 2009 | Legal Response/Decision |
Jul 21, 2009 | US Army Corp of Engineers Permit Date |
Jul 23, 2009 | US Army Corps of Engineers Approval Received |
Aug 10, 2009 | Stipulation Package from Biologist |
Aug 10, 2009 | Stipulation Package by Engineer |
Aug 12, 2009 | Permit Approved |
Aug 25, 2009 | Land Evidence Date |
Oct 08, 2009 | Commencement of Work Notice received |