Action Date | Action Description |
---|---|
Mar 14, 2007 | Assent Application Received |
Mar 15, 2007 | Administrative Review for Completeness |
Mar 15, 2007 | Team Review for Completeness |
Mar 15, 2007 | Team Review for Completeness |
Mar 15, 2007 | Application Accepted |
Mar 15, 2007 | Category A* (Docks) |
Mar 22, 2007 | HPHC Historical Preservation No Effect |
May 18, 2007 | Plans Received |
Jul 16, 2007 | Plans Received |
Jul 16, 2007 | Additional Information Received |
Jul 17, 2007 | 30 day Public Notice Issued |
Aug 03, 2007 | HPHC Historical Preservation No Effect |
Aug 17, 2007 | Public Notice End Date |
Nov 02, 2007 | Correspondence Received |
Nov 19, 2007 | US Army Corp of Engineers Permit Date |
Nov 23, 2007 | US Army Corps of Engineers Approval Received |
Dec 03, 2007 | Plans Received |
Dec 04, 2007 | Biologist Report |
Dec 04, 2007 | Engineering Report |
Dec 05, 2007 | Supervisor Biologist SignOff |
Dec 05, 2007 | Supervisor Engineer SignOff |
Dec 05, 2007 | Executive Signoff of Staff Reports |
Dec 27, 2007 | Ready to Schedule Semi-Monthly Meeting |
Dec 27, 2007 | Mail Agenda Notice |
Jan 02, 2008 | Mail Agenda Notice |
Jan 08, 2008 | Semi-Monthly Meeting Date Scheduled |
Jan 15, 2008 | Council Approval Granted |
Jan 15, 2008 | Semi-Monthly Meeting Date Scheduled |
Feb 13, 2008 | Plans Received |
Feb 18, 2008 | Correspondence Mailed/Faxed/E-mailed |
Feb 28, 2008 | Plans Received |
Mar 11, 2008 | Typist for Processing |
Mar 11, 2008 | Executive Sign Off |
Mar 11, 2008 | Sent to Photo Copy |
Mar 11, 2008 | Stipulation Package from Biologist |
Mar 11, 2008 | Stipulation Package by Engineer |
Mar 11, 2008 | Legal Response/Decision |
Mar 11, 2008 | Permit Approved |
May 19, 2008 | Land Evidence Date |