Action Date | Action Description |
---|---|
Oct 25, 2007 | Assent Application Received |
Oct 26, 2007 | Administrative Review for Completeness |
Oct 26, 2007 | Correspondence Mailed/Faxed/E-mailed |
Nov 02, 2007 | Note to File |
Nov 05, 2007 | Note to File |
Nov 08, 2007 | Application Accepted |
Nov 08, 2007 | Team Review for Completeness |
Nov 08, 2007 | Team Review for Completeness |
Nov 09, 2007 | Plans Received |
Nov 13, 2007 | Review on Hold |
Nov 24, 2007 | HPHC Historical Preservation No Effect |
Feb 06, 2008 | Additional Information Received |
Feb 19, 2008 | 30 day Public Notice Issued |
Mar 07, 2008 | Biologist Report |
Mar 10, 2008 | Public Hearing Notices Mailed |
Mar 17, 2008 | Executive Signoff of Staff Reports |
Mar 19, 2008 | Public Notice End Date |
Apr 08, 2008 | Engineering Report |
Apr 09, 2008 | Supervisor Biologist SignOff |
Apr 09, 2008 | Supervisor Engineer SignOff |
Apr 09, 2008 | Executive Signoff of Staff Reports |
Apr 17, 2008 | Water Quality Certification |
Apr 17, 2008 | Correspondence Received |
Apr 22, 2008 | Special Exception Scheduled for Semi-Monthly |
Apr 22, 2008 | Plans Received |
Apr 22, 2008 | Semi-Monthly Meeting Held |
Apr 22, 2008 | Council Approval Granted |
Apr 28, 2008 | Typist for Processing |
Apr 28, 2008 | Executive Sign Off |
Apr 28, 2008 | Sent to Photo Copy |
Apr 28, 2008 | Permit Approved |
May 28, 2008 | Stipulation Package from Biologist |
May 28, 2008 | Stipulation Package by Engineer |
Sep 22, 2008 | Letter of Authorization |
Oct 06, 2008 | Legal Response/Decision |
Nov 23, 2009 | Additional Information Received |
Dec 29, 2009 | Modification Request |
Dec 29, 2009 | Administrative Review for Completeness |
Jan 04, 2010 | Team Review for Completeness |
Jan 04, 2010 | Team Review for Completeness |
Mar 01, 2010 | Additional Information Received |
Mar 15, 2010 | Modification Approved |
Mar 15, 2010 | Biologist Report |
Mar 15, 2010 | Engineering Report |
Jun 01, 2010 | Land Evidence Date |