Action Date | Action Description |
---|---|
Dec 28, 2007 | Assent Application Received |
Jan 07, 2008 | Administrative Review for Completeness |
Jan 31, 2008 | Team Review for Completeness |
Feb 01, 2008 | Deficient Application - Owner Notification Sent |
Feb 28, 2008 | Deficiency Response Received |
Mar 11, 2008 | Administrative Review for Completeness |
Mar 11, 2008 | Plans Received |
Mar 12, 2008 | Team Review for Completeness |
Mar 12, 2008 | Team Review for Completeness |
Mar 12, 2008 | Application Accepted |
Mar 31, 2008 | Plans Received |
Apr 21, 2008 | 30 day Public Notice Issued |
Apr 21, 2008 | HPHC Historical Preservation No Effect |
May 21, 2008 | Public Notice End Date |
Jul 16, 2008 | Dock Meeting Scheduled (Admin) |
Sep 02, 2008 | US Army Corp of Engineers Permit Date |
Sep 08, 2008 | US Army Corps of Engineers Approval Received |
Sep 25, 2008 | Dock Meeting -- To Council |
Nov 19, 2008 | Correspondence Mailed/Faxed/E-mailed |
Mar 05, 2009 | Biologist Report |
Mar 16, 2009 | Engineering Report |
Mar 18, 2009 | Supervisor Biologist SignOff |
Mar 23, 2009 | Supervisor Engineer SignOff |
Mar 23, 2009 | Executive Signoff of Staff Reports |
Apr 13, 2009 | Ready to Schedule Semi-Monthly Meeting |
Apr 13, 2009 | Mail Agenda Notice |
Apr 28, 2009 | Semi-Monthly Meeting Held |
Apr 28, 2009 | Council Decision - Denied |
Apr 28, 2009 | Semi-Monthly Meeting Date Scheduled |
Mar 15, 2011 | Application Cancelled |