Action Date | Action Description |
---|---|
Dec 28, 2007 | Assent Application Received |
Jan 07, 2008 | Administrative Review for Completeness |
Jan 31, 2008 | Team Review for Completeness |
Feb 01, 2008 | Deficient Application - Owner Notification Sent |
Feb 28, 2008 | Deficiency Response Received |
Mar 11, 2008 | Plans Received |
Mar 17, 2008 | Application Accepted |
Mar 31, 2008 | Plans Received |
Apr 30, 2008 | 30 day Public Notice Issued |
May 15, 2008 | Objections/Comments Received |
May 21, 2008 | Objections/Comments Received |
Nov 03, 2008 | US Army Corp of Engineers Permit Date |
Nov 05, 2008 | US Army Corps of Engineers Approval Received |
Dec 19, 2008 | Correspondence Mailed/Faxed/E-mailed |
Mar 16, 2009 | Biologist Report |
Mar 16, 2009 | Engineering Report |
Mar 18, 2009 | Supervisor Biologist SignOff |
Mar 23, 2009 | Supervisor Engineer SignOff |
Mar 23, 2009 | Executive Signoff of Staff Reports |
Apr 13, 2009 | Ready to Schedule Semi-Monthly Meeting |
Apr 13, 2009 | Mail Agenda Notice |
Apr 28, 2009 | Semi-Monthly Meeting Held |
Apr 28, 2009 | Council Decision - Denied |
Apr 28, 2009 | Semi-Monthly Meeting Date Scheduled |
Mar 15, 2011 | Application Cancelled |