Action Date | Action Description |
---|---|
Jan 15, 2008 | Maintenance Certification Request |
Jan 16, 2008 | Administrative Review for Completeness |
Jan 16, 2008 | Team Review for Completeness |
Jan 16, 2008 | Team Review for Completeness |
Jan 16, 2008 | Deficient Application - Owner Notification Sent |
Jan 23, 2008 | Deficient Application Picked Up |
Jan 25, 2008 | Deficiency Response Received |
Jan 28, 2008 | Team Review for Completeness |
Jan 28, 2008 | Team Review for Completeness |
Jan 28, 2008 | Application Accepted |
Jan 28, 2008 | Biologist Report |
Jan 28, 2008 | Engineering Report |
Jan 28, 2008 | Typist for Processing |
Jan 28, 2008 | Executive Sign Off |
Jan 28, 2008 | Sent to Photo Copy |
Jan 28, 2008 | Permit Approved |
Feb 04, 2008 | Land Evidence Date |