Jan 22, 2008 | Assent Application Received |
Jan 23, 2008 | Administrative Review for Completeness |
Jan 23, 2008 | Team Review for Completeness |
Jan 23, 2008 | Team Review for Completeness |
Jan 23, 2008 | Application Accepted |
Feb 01, 2008 | Additional Information Requested from Applicant |
Feb 01, 2008 | HPHC Historical Preservation No Effect |
Jul 10, 2008 | Engineering Report |
Jul 10, 2008 | Biologist Report |
Jul 11, 2008 | Typist for Processing |
Jul 11, 2008 | Executive Sign Off |
Jul 11, 2008 | Sent to Photo Copy |
Jul 11, 2008 | Permit Approved |
Aug 08, 2008 | Land Evidence Date |