Action Date | Action Description |
---|---|
Monitoring Report | |
Jan 30, 2008 | Assent Application Received |
Jan 31, 2008 | Administrative Review for Completeness |
Feb 05, 2008 | Team Review for Completeness |
Feb 05, 2008 | Application Accepted |
Feb 07, 2008 | 30 day Public Notice Issued |
Feb 14, 2008 | HPHC Historical Preservation No Effect |
Feb 26, 2008 | Additional Information Received |
Mar 07, 2008 | Public Notice End Date |
Apr 14, 2008 | Engineering Report |
Apr 15, 2008 | Biologist Report |
Apr 21, 2008 | US Army Corp of Engineers Permit Date |
Apr 23, 2008 | US Army Corps of Engineers Approval Received |
Apr 29, 2008 | Dock/1.1.6 Review approval |
Apr 29, 2008 | Scheduled for Section 110 Review meeting |
May 05, 2008 | Typist for Processing |
May 05, 2008 | Executive Sign Off |
May 05, 2008 | Sent to Photo Copy |
May 05, 2008 | Permit Approved |
Aug 22, 2008 | Duplicate Original Assent requested/mailed |
Aug 27, 2008 | Land Evidence Date |
Nov 24, 2008 | Commencement of Work Notice received |
Dec 08, 2009 | Letter of Authorization |
Nov 18, 2010 | Monitoring Report |
Nov 01, 2011 | Monitoring Report |