Action Date | Action Description |
---|---|
Jan 31, 2008 | Assent Application Received |
Feb 01, 2008 | Administrative Review for Completeness |
Feb 06, 2008 | Team Review for Completeness |
Feb 06, 2008 | Team Review for Completeness |
Feb 06, 2008 | Application Accepted |
Mar 12, 2008 | 30-Day Notification of Cancellation letter |
Jun 05, 2008 | Plans Received |
Jun 12, 2008 | Typist for Processing |
Jun 12, 2008 | Executive Sign Off |
Jun 12, 2008 | Sent to Photo Copy |
Jun 12, 2008 | Permit Approved |
Jun 12, 2008 | Biologist Report |
Jun 12, 2008 | Engineering Report |
Jun 19, 2008 | Land Evidence Date |
Sep 22, 2008 | US Army Corp of Engineers Permit Date |
Sep 24, 2008 | US Army Corps of Engineers Approval Received |