Feb 06, 2008 | Assent Application Received |
Feb 07, 2008 | Administrative Review for Completeness |
Feb 14, 2008 | Team Review for Completeness |
Feb 15, 2008 | Deficient Application - Owner Notification Sent |
Feb 21, 2008 | Deficient Application Picked Up |
Jul 29, 2009 | Deficiency Response Received |
Sep 01, 2009 | Team Review for Completeness |
Sep 01, 2009 | Application Accepted |
Oct 05, 2009 | HPHC Historical Preservation No Effect |
Oct 23, 2009 | Typist for Processing |
Oct 23, 2009 | Biologist Report |
Oct 26, 2009 | Executive Sign Off |
Oct 26, 2009 | Sent to Photo Copy |
Oct 26, 2009 | Permit Approved |
Nov 16, 2009 | Land Evidence Date |
Aug 14, 2012 | Extension of Permit Request |
Aug 16, 2012 | Extension Toll letter mailed |
Jul 11, 2014 | Freshwater Wetland - Permit Modification Request |
Jul 14, 2014 | Administrative Review for Completeness |
Jul 21, 2014 | Team Review for Completeness |
Jul 30, 2014 | Biologist Report |
Aug 04, 2014 | Typist for Processing |
Aug 04, 2014 | Executive Sign Off |
Aug 04, 2014 | Sent to Photo Copy |
Aug 04, 2014 | Modification Approved |
Aug 15, 2014 | Land Evidence Date |