Action Date | Action Description |
---|---|
Mar 14, 2008 | Assent Application Received |
Mar 17, 2008 | Administrative Review for Completeness |
Apr 23, 2008 | Plans Received |
Apr 24, 2008 | Application Accepted |
Apr 24, 2008 | Team Review for Completeness |
Apr 24, 2008 | Category A* (Docks) |
May 01, 2008 | 30 day Public Notice Issued |
May 09, 2008 | HPHC Historical Preservation No Effect |
May 31, 2008 | Public Notice End Date |
Jul 16, 2008 | Dock Meeting -- Approval |
Jul 21, 2008 | US Army Corp of Engineers Permit Date |
Jul 22, 2008 | Typist for Processing |
Jul 22, 2008 | Executive Sign Off |
Jul 22, 2008 | Sent to Photo Copy |
Jul 22, 2008 | Permit Approved |
Jul 22, 2008 | Biologist Report |
Jul 22, 2008 | Engineering Report |
Jul 25, 2008 | US Army Corps of Engineers Approval Received |
Nov 25, 2008 | Land Evidence Date |
Aug 05, 2009 | Modification Request |
Aug 06, 2009 | Administrative Review for Completeness |
Aug 12, 2009 | Team Review for Completeness |
Sep 03, 2009 | HPHC Historical Preservation No Effect |
May 08, 2010 | Certified Receipt Received |
Feb 10, 2011 | Modification Canceled |
Feb 10, 2011 | 30-Day Notification of Cancellation letter |
Feb 10, 2011 | Engineering Report |
Feb 16, 2011 | Certified Receipt Received |