Action Date | Action Description |
---|---|
Mar 21, 2008 | Assent Application Received |
Mar 24, 2008 | Administrative Review for Completeness |
Mar 24, 2008 | Team Review for Completeness |
Mar 24, 2008 | Application Accepted |
Apr 16, 2008 | Engineering Report |
Apr 17, 2008 | Typist for Processing |
Apr 17, 2008 | Executive Sign Off |
Apr 17, 2008 | Sent to Photo Copy |
Apr 17, 2008 | Permit Approved |
Apr 24, 2008 | Land Evidence Date |
Apr 28, 2008 | Commencement of Work Notice received |
May 01, 2008 | HPHC Historical Preservation No Effect |