Action Date | Action Description |
---|---|
Mar 31, 2008 | Assent Application Received |
Apr 01, 2008 | Administrative Review for Completeness |
Apr 01, 2008 | Team Review for Completeness |
Apr 01, 2008 | Team Review for Completeness |
Apr 01, 2008 | Application Accepted |
Apr 01, 2008 | Category A* (Docks) |
May 05, 2008 | HPHC Historical Preservation No Effect |
May 16, 2008 | Plans Received |
May 20, 2008 | 30 day Public Notice Issued |
Jun 20, 2008 | Public Notice End Date |
Jun 23, 2008 | Dock Meeting Scheduled (Admin) |
Jun 23, 2008 | Typist for Processing |
Jun 23, 2008 | Executive Sign Off |
Jun 23, 2008 | Sent to Photo Copy |
Jun 23, 2008 | Permit Approved |
Jun 23, 2008 | Biologist Report |
Jun 23, 2008 | Engineering Report |
Jul 09, 2008 | Land Evidence Date |
Aug 05, 2008 | US Army Corp of Engineers Permit Date |
Aug 07, 2008 | US Army Corps of Engineers Approval Received |
Aug 28, 2009 | Modification Request |
Aug 31, 2009 | Administrative Review for Completeness |
Aug 31, 2009 | Team Review for Completeness |
Aug 31, 2009 | Team Review for Completeness |
Sep 11, 2009 | HPHC Historical Preservation No Effect |
Feb 19, 2010 | Additional Information Received |
Feb 24, 2010 | 30 day Public Notice Issued |
Mar 24, 2010 | Public Notice End Date |
Apr 05, 2010 | Dock Meeting -- Approval |
Apr 06, 2010 | Modification Approved |
Apr 06, 2010 | Biologist Report |
Apr 06, 2010 | Engineering Report |
Apr 15, 2010 | US Army Corp of Engineers Permit Date |
Jun 14, 2010 | Land Evidence Date |
Oct 07, 2010 | Commencement of Work Notice received |