Action Date | Action Description |
---|---|
Apr 04, 2008 | Assent Application Received |
Apr 07, 2008 | Administrative Review for Completeness |
Apr 17, 2008 | Team Review for Completeness |
Apr 17, 2008 | Team Review for Completeness |
Apr 17, 2008 | Plans Received |
Apr 17, 2008 | Application Accepted |
May 28, 2008 | HPHC Historical Preservation No Effect |
Jun 04, 2008 | Correspondence Received |
Jun 04, 2008 | Biologist Report |
Jun 04, 2008 | Engineering Report |
Jun 05, 2008 | Plans Received |
Jun 20, 2008 | Supervisor Biologist SignOff |
Jun 20, 2008 | Supervisor Engineer SignOff |
Jun 24, 2008 | Executive Signoff of Staff Reports |
Oct 02, 2008 | Ready to Schedule Semi-Monthly Meeting |
Oct 02, 2008 | Mail Agenda Notice |
Oct 14, 2008 | Council Approval Granted |
Oct 14, 2008 | Semi-Monthly Meeting Held |
Oct 14, 2008 | Semi-Monthly Meeting Date Scheduled |
Nov 13, 2008 | Legal Response/Decision |
Jan 09, 2009 | Plans Received |
Jan 21, 2009 | Additional Information Received |
Jan 22, 2009 | Typist for Processing |
Jan 22, 2009 | Executive Sign Off |
Jan 22, 2009 | Sent to Photo Copy |
Jan 22, 2009 | Permit Approved |
Jan 22, 2009 | Stipulation Package from Biologist |
Jan 22, 2009 | Stipulation Package by Engineer |
Feb 27, 2009 | Land Evidence Date |