Action Date | Action Description |
---|---|
Apr 02, 2008 | Freshwater Wetland - Request to Alter |
Apr 02, 2008 | Administrative Review for Completeness |
Apr 02, 2008 | Team Review for Completeness |
Apr 02, 2008 | Team Review for Completeness |
Apr 02, 2008 | Application Accepted |
Jun 09, 2008 | 30 day Public Notice Issued |
Aug 07, 2008 | Biologist Report |
Aug 07, 2008 | Engineering Report |
Aug 07, 2008 | Correspondence Received |
Aug 08, 2008 | Public Notice End Date |
Aug 08, 2008 | Executive Signoff of Staff Reports |
Aug 25, 2008 | Ready to Schedule Semi-Monthly Meeting |
Aug 25, 2008 | Mail Agenda Notice |
Sep 03, 2008 | Continuance Requested |
Sep 09, 2008 | Semi-Monthly Meeting Date Scheduled |
Jan 30, 2009 | Correspondence Received |
Feb 09, 2009 | Correspondence Received |
Feb 10, 2009 | Mail Agenda Notice |
Feb 10, 2009 | Ready to Schedule Semi-Monthly Meeting |
Feb 24, 2009 | Semi-Monthly Meeting Postponed |
Feb 24, 2009 | Semi-Monthly Meeting Date Scheduled |
Feb 24, 2009 | Mail Agenda Notice |
Mar 23, 2009 | US Army Corp of Engineers Permit Date |
Mar 24, 2009 | Semi-Monthly Meeting Postponed |
Mar 24, 2009 | Semi-Monthly Meeting Date Scheduled |
Mar 25, 2009 | US Army Corps of Engineers Approval Received |
Mar 26, 2009 | Mail Agenda Notice |
Mar 31, 2009 | Mail Agenda Notice |
Apr 07, 2009 | Council Approval Granted |
Apr 07, 2009 | Semi-Monthly Meeting Date Scheduled |
Apr 07, 2009 | Semi-Monthly Meeting Held |
May 19, 2009 | Stipulation Package from Biologist |
May 19, 2009 | Stipulation Package by Engineer |
May 22, 2009 | Typist for Processing |
May 22, 2009 | Permit Approved |
May 27, 2009 | Executive Sign Off |
May 29, 2009 | Sent to Photo Copy |
May 29, 2009 | Land Evidence Date |
Sep 15, 2009 | Commencement of Work Notice received |
Jan 27, 2010 | Legal Response/Decision |