Action Date | Action Description |
---|---|
May 13, 2008 | Assent Application Received |
May 13, 2008 | Administrative Review for Completeness |
May 13, 2008 | Team Review for Completeness |
May 13, 2008 | Team Review for Completeness |
May 13, 2008 | Application Accepted |
May 22, 2008 | HPHC Historical Preservation No Effect |
Jul 16, 2008 | Typist for Processing |
Jul 16, 2008 | Executive Sign Off |
Jul 16, 2008 | Sent to Photo Copy |
Jul 16, 2008 | Permit Approved |
Jul 16, 2008 | Biologist Report |
Jul 16, 2008 | Engineering Report |
Jul 31, 2008 | Land Evidence Date |
Nov 12, 2008 | Modification Request |
Nov 13, 2008 | Administrative Review for Completeness |
Nov 13, 2008 | Team Review for Completeness |
Nov 13, 2008 | Team Review for Completeness |
Nov 17, 2008 | Engineering Report |
Nov 17, 2008 | Biologist Report |
Nov 18, 2008 | HPHC Historical Preservation No Effect |
Nov 20, 2008 | Typist for Processing |
Nov 20, 2008 | Executive Sign Off |
Nov 20, 2008 | Sent to Photo Copy |
Nov 20, 2008 | Modification Approved |
Dec 02, 2008 | Land Evidence Date |
Dec 02, 2008 | Executive Sign Off |