Action Date | Action Description |
---|---|
May 22, 2008 | Assent Application Received |
May 23, 2008 | Administrative Review for Completeness |
May 23, 2008 | Team Review for Completeness |
May 23, 2008 | Team Review for Completeness |
May 23, 2008 | Application Accepted |
Jun 11, 2008 | Additional Information Received |
Jun 24, 2008 | Additional Information Received |
Jun 30, 2008 | Plans Received |
Jun 30, 2008 | HPHC Historical Preservation No Effect |
Jul 07, 2008 | Engineering Report |
Jul 09, 2008 | Biologist Report |
Jul 10, 2008 | Typist for Processing |
Jul 10, 2008 | Executive Sign Off |
Jul 10, 2008 | Sent to Photo Copy |
Jul 10, 2008 | Permit Approved |
Feb 27, 2009 | Land Evidence Date |
Aug 15, 2011 | Modification Request |
Aug 17, 2011 | Administrative Review for Completeness |
Aug 22, 2011 | Team Review for Completeness |
Aug 22, 2011 | Team Review for Completeness |
Sep 07, 2011 | HPHC Historical Preservation No Effect |
Sep 14, 2011 | Additional Information Received |
Sep 19, 2011 | Additional Information Received |
Oct 04, 2011 | Additional Information Received |
Oct 05, 2011 | Biologist Report |
Oct 05, 2011 | Engineering Report |
Oct 06, 2011 | Typist for Processing |
Oct 06, 2011 | Modification Approved |
Oct 12, 2011 | Executive Sign Off |
Oct 12, 2011 | Sent to Photo Copy |
Oct 20, 2011 | Land Evidence Date |
Oct 20, 2011 | Duplicate Original Assent requested/mailed |
Jun 18, 2012 | Additional Information Received |