Action Date | Action Description |
---|---|
Jun 25, 2008 | Dredge Application |
Jun 30, 2008 | Administrative Review for Completeness |
Jun 30, 2008 | Team Review for Completeness |
Jun 30, 2008 | Application Accepted |
Jul 18, 2008 | Joint Public Notice |
Jul 30, 2008 | Correspondence Received |
Aug 15, 2008 | Objections/Comments Received |
Aug 18, 2008 | Public Notice End Date |
Aug 19, 2008 | Public Notice End Date |
Sep 18, 2008 | Correspondence Received |
Oct 17, 2008 | Joint Public Notice |
Nov 17, 2008 | Public Notice End Date |
Apr 09, 2009 | Correspondence Received |
Dec 22, 2009 | Engineering Report |
Dec 29, 2009 | Typist for Processing |
Dec 29, 2009 | Executive Sign Off |
Dec 29, 2009 | Sent to Photo Copy |
Dec 29, 2009 | Permit Approved |
Jan 13, 2010 | Land Evidence Date |