Action Date | Action Description |
---|---|
Jun 25, 2008 | Maintenance Certification Request |
Jun 26, 2008 | Administrative Review for Completeness |
Jul 01, 2008 | Team Review for Completeness |
Jul 01, 2008 | Team Review for Completeness |
Jul 01, 2008 | Deficient Application - Owner Notification Sent |
Jul 24, 2008 | Deficiency Response Received |
Jul 28, 2008 | Administrative Review for Completeness |
Aug 04, 2008 | Team Review for Completeness |
Aug 04, 2008 | Team Review for Completeness |
Aug 04, 2008 | Application Accepted |
Aug 14, 2008 | Biologist Report |
Aug 14, 2008 | Engineering Report |
Aug 15, 2008 | Typist for Processing |
Aug 15, 2008 | Executive Sign Off |
Aug 15, 2008 | Sent to Photo Copy |
Aug 15, 2008 | Permit Approved |
Aug 22, 2008 | HPHC Historical Preservation No Effect |
Sep 09, 2008 | Land Evidence Date |
Oct 06, 2008 | Commencement of Work Notice received |
May 26, 2009 | Modification Request |
May 27, 2009 | Administrative Review for Completeness |
May 27, 2009 | Team Review for Completeness |
May 27, 2009 | Team Review for Completeness |
Jun 01, 2009 | Biologist Report |
Jun 01, 2009 | Engineering Report |
Jun 03, 2009 | Typist for Processing |
Jun 03, 2009 | Executive Sign Off |
Jun 03, 2009 | Modification Approved |
Jun 04, 2009 | Sent to Photo Copy |
Jun 08, 2009 | HPHC Historical Preservation No Effect |
Jun 15, 2009 | Land Evidence Date |