Action Date | Action Description |
---|---|
Jul 16, 2008 | Assent Application Received |
Jul 17, 2008 | Administrative Review for Completeness |
Jul 17, 2008 | Team Review for Completeness |
Jul 17, 2008 | Team Review for Completeness |
Jul 17, 2008 | Application Accepted |
Jul 21, 2008 | Category A* (Docks) |
Aug 01, 2008 | HPHC Historical Preservation No Effect |
Aug 05, 2008 | 30 day Public Notice Issued |
Sep 05, 2008 | Public Notice End Date |
Sep 24, 2008 | US Army Corp of Engineers Permit Date |
Sep 25, 2008 | Dock Meeting Scheduled (Admin) |
Oct 01, 2008 | US Army Corps of Engineers Approval Received |
Dec 18, 2008 | Plans Received |
Jan 16, 2009 | Typist for Processing |
Jan 16, 2009 | Executive Sign Off |
Jan 16, 2009 | Sent to Photo Copy |
Jan 16, 2009 | Permit Approved |
Jan 16, 2009 | Biologist Report |
Jan 16, 2009 | Engineering Report |
Feb 03, 2009 | Land Evidence Date |
Oct 29, 2009 | Commencement of Work Notice received |
Apr 19, 2010 | Modification Request |
Apr 22, 2010 | Administrative Review for Completeness |
Apr 22, 2010 | Team Review for Completeness |
Apr 22, 2010 | Team Review for Completeness |
May 04, 2010 | HPHC Historical Preservation No Effect |
May 07, 2010 | Additional Information Received |
May 11, 2010 | 30 day Public Notice Issued |
May 26, 2010 | US Army Corp of Engineers Permit Date |
Jun 01, 2010 | US Army Corps of Engineers Approval Received |
Jun 11, 2010 | Public Notice End Date |
Jun 22, 2010 | Dock Meeting -- Approval |
Jun 23, 2010 | Modification Approved |
Jun 23, 2010 | Biologist Report |
Jun 23, 2010 | Engineering Report |
Jul 02, 2010 | Land Evidence Date |