Action Date | Action Description |
---|---|
Aug 18, 2008 | Assent Application Received |
Aug 19, 2008 | Administrative Review for Completeness |
Aug 27, 2008 | Deficient Application - Owner Notification Sent |
Aug 29, 2008 | Deficient Application Picked Up |
Oct 06, 2008 | Deficiency Response Received |
Oct 09, 2008 | Administrative Review for Completeness |
Oct 20, 2008 | Team Review for Completeness |
Oct 20, 2008 | Team Review for Completeness |
Oct 20, 2008 | Application Accepted |
Oct 20, 2008 | Category B assigned |
Nov 07, 2008 | 30 day Public Notice Issued |
Nov 18, 2008 | HPHC Historical Preservation No Effect |
Nov 24, 2008 | Correspondence Mailed/Faxed/E-mailed |
Dec 08, 2008 | Public Notice End Date |
Jan 14, 2009 | Correspondence Received |
Jan 16, 2009 | Public Notice End Date Extension Granted |
Feb 11, 2009 | Additional Information Received |
Mar 02, 2009 | Biologist Report |
Mar 10, 2009 | Plans Received |
Apr 29, 2009 | Engineering Report |
May 11, 2009 | Executive Signoff of Staff Reports |
May 19, 2009 | Ready to Schedule Semi-Monthly Meeting |
May 19, 2009 | Mail Agenda Notice |
Jun 01, 2009 | Entry of Appearance Received |
Jun 10, 2009 | Semi-Monthly Meeting Held |
Jun 10, 2009 | Council Approval Granted |
Jun 10, 2009 | Semi-Monthly Meeting Date Scheduled |
Jun 11, 2009 | Correspondence Received |
Jun 26, 2009 | Stipulation Package from Biologist |
Jun 26, 2009 | Stipulation Package by Engineer |
Jun 29, 2009 | Typist for Processing |
Jun 29, 2009 | Executive Sign Off |
Jun 29, 2009 | Sent to Photo Copy |
Jun 29, 2009 | Permit Approved |
Sep 18, 2009 | Land Evidence Date |
Dec 03, 2010 | Modification Request |
Dec 06, 2010 | Administrative Review for Completeness |
Dec 13, 2010 | Team Review for Completeness |
Dec 13, 2010 | Biologist Report |
Dec 13, 2010 | Engineering Report |
Dec 13, 2010 | Modification Approved |
Dec 15, 2010 | Typist for Processing |
Dec 15, 2010 | Executive Sign Off |
Dec 15, 2010 | Sent to Photo Copy |
Apr 05, 2011 | Land Evidence Date |
Apr 04, 2012 | Extension Toll letter mailed |
Jan 30, 2014 | Correspondence Mailed/Faxed/E-mailed |
May 31, 2019 | Expiration of Assent/End of Tolling Legislation |