Action Date | Action Description |
---|---|
Aug 08, 2008 | Correspondence Received |
Aug 18, 2008 | Assent Application Received |
Aug 19, 2008 | Administrative Review for Completeness |
Aug 21, 2008 | Team Review for Completeness |
Aug 28, 2008 | Team Review for Completeness |
Aug 28, 2008 | Application Accepted |
Aug 28, 2008 | Category A* (Docks) |
Aug 29, 2008 | Additional Information Received |
Sep 03, 2008 | Additional Information Received |
Sep 04, 2008 | Additional Information Received |
Sep 05, 2008 | 30 day Public Notice Issued |
Sep 12, 2008 | HPHC Historical Preservation No Effect |
Oct 05, 2008 | Public Notice End Date |
Oct 06, 2008 | Objections/Comments Received |
Oct 07, 2008 | Objections/Comments Received |
Oct 27, 2008 | US Army Corp of Engineers Permit Date |
Oct 29, 2008 | US Army Corps of Engineers Approval Received |
Dec 01, 2008 | Biologist Report |
Dec 01, 2008 | Engineering Report |
Dec 02, 2008 | Plans Received |
Dec 03, 2008 | Supervisor Biologist SignOff |
Dec 11, 2008 | Supervisor Engineer SignOff |
Dec 12, 2008 | Executive Signoff of Staff Reports |
Dec 22, 2008 | Ready to Schedule Semi-Monthly Meeting |
Dec 22, 2008 | Mail Agenda Notice |
Dec 29, 2008 | Correspondence Received |
Jan 13, 2009 | Council Approval Granted |
Jan 13, 2009 | Semi-Monthly Meeting Held |
Jan 13, 2009 | Semi-Monthly Meeting Date Scheduled |
Jan 21, 2009 | Legal Response/Decision |
Jan 29, 2009 | Plans Received |
Jan 29, 2009 | Typist for Processing |
Jan 29, 2009 | Executive Sign Off |
Jan 29, 2009 | Sent to Photo Copy |
Jan 29, 2009 | Permit Approved |
Jan 29, 2009 | Stipulation Package from Biologist |
Jan 29, 2009 | Stipulation Package by Engineer |
Feb 10, 2009 | Land Evidence Date |