Action Date | Action Description |
---|---|
Aug 21, 2008 | Assent Application Received |
Aug 22, 2008 | Administrative Review for Completeness |
Aug 22, 2008 | Team Review for Completeness |
Aug 22, 2008 | Application Accepted |
Sep 10, 2008 | Biologist Report |
Sep 10, 2008 | Typist for Processing |
Sep 10, 2008 | Executive Sign Off |
Sep 10, 2008 | Sent to Photo Copy |
Sep 10, 2008 | Permit Approved |
Sep 12, 2008 | HPHC Historical Preservation No Effect |
Sep 15, 2008 | Land Evidence Date |
Jan 13, 2014 | Extension Toll letter mailed |