Action Date | Action Description |
---|---|
Sep 18, 2008 | Assent Application Received |
Sep 19, 2008 | Administrative Review for Completeness |
Sep 19, 2008 | Team Review for Completeness |
Sep 19, 2008 | Team Review for Completeness |
Sep 19, 2008 | Application Accepted |
Sep 26, 2008 | Biologist Report |
Sep 26, 2008 | Engineering Report |
Oct 01, 2008 | Typist for Processing |
Oct 01, 2008 | Executive Sign Off |
Oct 01, 2008 | Sent to Photo Copy |
Oct 01, 2008 | Permit Approved |
Oct 03, 2008 | HPHC Historical Preservation No Effect |
Dec 18, 2008 | Land Evidence Date |