Action Date | Action Description |
---|---|
Oct 02, 2008 | Dredge Application |
Oct 06, 2008 | Administrative Review for Completeness |
Oct 20, 2008 | Team Review for Completeness |
Oct 20, 2008 | Application Accepted |
Oct 31, 2008 | Joint Public Notice |
Oct 31, 2008 | HPHC Historical Preservation No Effect |
Nov 07, 2008 | Objections/Comments Received |
Nov 30, 2008 | Public Notice End Date |
Dec 29, 2008 | US Army Corp of Engineers Permit Date |
Dec 30, 2008 | Typist for Processing |
Dec 30, 2008 | Executive Sign Off |
Dec 30, 2008 | Sent to Photo Copy |
Dec 30, 2008 | Dredge Report |
Dec 30, 2008 | Permit Approved |
Dec 31, 2008 | Water Quality Certification |
Dec 31, 2008 | US Army Corps of Engineers Approval Received |
Feb 20, 2009 | Land Evidence Date |
Oct 05, 2011 | Extension Toll letter mailed |
Feb 23, 2012 | Correspondence Mailed/Faxed/E-mailed |