Action Date | Action Description |
---|---|
Nov 19, 2008 | Assent Application Received |
Nov 20, 2008 | Administrative Review for Completeness |
Nov 21, 2008 | Team Review for Completeness |
Nov 21, 2008 | Team Review for Completeness |
Nov 21, 2008 | Application Accepted |
Dec 22, 2008 | HPHC Historical Preservation No Effect |
Dec 22, 2008 | HPHC Historical Preservation No Effect |
Dec 23, 2008 | Biologist Report |
Dec 24, 2008 | Engineering Report |
Dec 26, 2008 | Typist for Processing |
Dec 26, 2008 | Executive Sign Off |
Dec 26, 2008 | Sent to Photo Copy |
Dec 26, 2008 | Permit Approved |
Jan 22, 2009 | Land Evidence Date |
Jun 10, 2011 | Extension Toll letter mailed |