Action Date | Action Description |
---|---|
Enforcement Compliance Inspection Required | |
Nov 21, 2008 | Assent Application Received |
Nov 25, 2008 | Additional Information Requested from Applicant |
Dec 16, 2008 | Correspondence Received |
Dec 17, 2008 | Team Review for Completeness |
Dec 17, 2008 | Team Review for Completeness |
Dec 17, 2008 | Application Accepted |
Dec 17, 2008 | Administrative Review for Completeness |
Jan 21, 2009 | HPHC Historical Preservation No Effect |
Apr 29, 2009 | Biologist Report |
Apr 29, 2009 | Engineering Report |
May 03, 2009 | Supervisor Engineer SignOff |
May 20, 2009 | Supervisor Biologist SignOff |
Jun 30, 2009 | Executive Signoff of Staff Reports |
Jul 20, 2009 | Ready to Schedule Semi-Monthly Meeting |
Jul 20, 2009 | Mail Agenda Notice |
Jul 28, 2009 | Continued Application by the Council |
Jul 28, 2009 | Semi-Monthly Meeting Date Scheduled |
Oct 06, 2010 | Ready to Schedule Semi-Monthly Meeting |
Oct 14, 2010 | Typist for Processing |
Oct 14, 2010 | Permit Approved |
Oct 18, 2010 | Executive Sign Off |
Oct 18, 2010 | Sent to Photo Copy |
Oct 29, 2010 | Land Evidence Date |
Sep 23, 2011 | Correspondence Received |
Jul 01, 2014 | Extension Toll letter mailed |
Apr 05, 2018 | Correspondence Received |
May 01, 2018 | Extension Toll letter mailed |
Nov 05, 2018 | Correspondence Received |
Jun 28, 2019 | Extension of Permit Request |
Mar 16, 2021 | Modification Request |
Mar 16, 2021 | Administrative Review for Completeness |
Apr 27, 2021 | Correspondence Mailed/Faxed/E-mailed |
Apr 27, 2021 | Process Extension |
Apr 27, 2021 | Extension Approved |
May 21, 2021 | Correspondence Mailed/Faxed/E-mailed |
May 21, 2021 | Bio Team Review for Completeness |
Sep 16, 2021 | Additional Information Received |
May 16, 2022 | Additional Information Received |
Aug 26, 2022 | Biologist Report |
Aug 30, 2022 | Typist for Processing |
Aug 30, 2022 | Executive Sign Off |
Aug 30, 2022 | Sent to Photo Copy |
Aug 30, 2022 | Modification Approved |
Jan 17, 2023 | Land Evidence Date |