Feb 04, 2009 | Assent Application Received |
Feb 05, 2009 | Administrative Review for Completeness |
Feb 05, 2009 | Team Review for Completeness |
Feb 05, 2009 | Application Accepted |
Feb 16, 2009 | HPHC Historical Preservation No Effect |
Mar 25, 2009 | Additional Information Requested from Applicant |
Sep 01, 2009 | 30-Day Notification of Cancellation letter |
Sep 11, 2009 | Certified Receipt Received |
Sep 29, 2009 | Correspondence Received |
Dec 21, 2009 | Additional Information Received |
Apr 06, 2010 | Note to File |
Aug 31, 2010 | Additional Information Received |
Oct 01, 2010 | Correspondence Received |
Oct 01, 2010 | Correspondence Mailed/Faxed/E-mailed |
Jan 20, 2011 | Engineering Report |
Jan 24, 2011 | Biologist Report |
Jan 28, 2011 | Typist for Processing |
Jan 28, 2011 | Permit Approved |
Jan 31, 2011 | Executive Sign Off |
Jan 31, 2011 | Sent to Photo Copy |
Feb 23, 2011 | Land Evidence Date |
Feb 23, 2011 | Objections/Comments Received |
Oct 18, 2013 | Plans Received |
Nov 21, 2013 | Duplicate Original Assent requested/mailed |
Apr 10, 2014 | Extension Toll letter mailed |
Mar 23, 2015 | Plans Received |
Apr 13, 2015 | Modification Request |
Apr 15, 2015 | Plans Received |
Apr 17, 2015 | Administrative Review for Completeness |
Apr 24, 2015 | Team Review for Completeness |
May 18, 2015 | Biologist Report |
May 21, 2015 | Typist for Processing |
May 21, 2015 | Modification Approved |
May 26, 2015 | Executive Sign Off |
May 26, 2015 | Sent to Photo Copy |
Dec 02, 2015 | Land Evidence Date |