Action Date | Action Description |
---|---|
Feb 04, 2009 | Maintenance Certification Request |
Feb 05, 2009 | Administrative Review for Completeness |
Feb 05, 2009 | Team Review for Completeness |
Feb 05, 2009 | Team Review for Completeness |
Feb 10, 2009 | Deficient Application - Owner Notification Sent |
Feb 20, 2009 | Deficient Application Picked Up |
Apr 15, 2009 | Deficiency Response Received |
Apr 16, 2009 | Administrative Review for Completeness |
Apr 16, 2009 | Team Review for Completeness |
Apr 16, 2009 | Finding Of No Significant Impact (FONSI) |
Apr 16, 2009 | Application Accepted |