Action Date | Action Description |
---|---|
Jul 15, 2009 | Maintenance Certification Request |
Jul 17, 2009 | Administrative Review for Completeness |
Jul 17, 2009 | Team Review for Completeness |
Jul 17, 2009 | Team Review for Completeness |
Jul 17, 2009 | Application Accepted |
Jul 29, 2009 | Biologist Report |
Jul 29, 2009 | Engineering Report |
Jul 30, 2009 | Typist for Processing |
Jul 30, 2009 | Executive Sign Off |
Jul 30, 2009 | Sent to Photo Copy |
Jul 30, 2009 | Permit Approved |
Aug 27, 2009 | HPHC Historical Preservation No Effect |