Action Date | Action Description |
---|---|
Aug 05, 2009 | Maintenance Certification Request |
Aug 06, 2009 | Administrative Review for Completeness |
Aug 06, 2009 | Team Review for Completeness |
Aug 06, 2009 | Team Review for Completeness |
Aug 06, 2009 | Application Accepted |
Sep 02, 2009 | Biologist Report |
Sep 03, 2009 | Typist for Processing |
Sep 03, 2009 | Executive Sign Off |
Sep 04, 2009 | Sent to Photo Copy |
Sep 09, 2009 | HPHC Historical Preservation Comments/Concerns |
Sep 09, 2009 | Review on Hold |
Jan 11, 2011 | HPHC Historical Preservation Comments/Concerns |
Mar 25, 2011 | Historical Preservation Conditional Approval |
May 02, 2011 | Engineering Report |
Jun 14, 2011 | Permit Approved |
Jun 14, 2011 | Typist for Processing |
Jun 15, 2011 | Executive Sign Off |
Jun 15, 2011 | Sent to Photo Copy |
Aug 07, 2012 | Historical Preservation Conditional Approval |
Aug 23, 2012 | Historical Preservation Conditional Approval |
Sep 12, 2012 | Historical Preservation Conditional Approval |