Action Date | Action Description |
---|---|
Oct 27, 2011 | Assent Application Received |
Oct 31, 2011 | Administrative Review for Completeness |
Nov 01, 2011 | Team Review for Completeness |
Nov 01, 2011 | Application Accepted |
Dec 27, 2011 | 30 day Public Notice Issued |
Jan 04, 2012 | HPHC Historical Preservation No Effect |
Jan 27, 2012 | Public Notice End Date |
Apr 30, 2012 | Dredge Report |
Apr 30, 2012 | DEM Dredge Permit |
May 03, 2012 | Dredge Permit Issued |
May 07, 2012 | Typist for Processing |
May 07, 2012 | Executive Sign Off |
May 07, 2012 | Sent to Photo Copy |
May 07, 2012 | Permit Approved |
Jun 01, 2012 | Land Evidence Date |
Apr 24, 2013 | CAD Cell Fee Due-Final |
Oct 09, 2018 | Correspondence Received |
Dec 18, 2018 | Extension of Permit Request |
Jan 08, 2019 | Extension Approved |
Feb 18, 2020 | Plans Received |
Mar 09, 2020 | CAD Cell Fee Due-Final |