Action Date | Action Description |
---|---|
Oct 28, 2011 | Assent Application Received |
Oct 31, 2011 | Administrative Review for Completeness |
Oct 31, 2011 | Additional Information Received |
Nov 01, 2011 | Team Review for Completeness |
Nov 02, 2011 | Team Review for Completeness |
Nov 02, 2011 | Application Accepted |
Nov 02, 2011 | Biologist Report |
Nov 02, 2011 | Engineering Report |
Nov 03, 2011 | Typist for Processing |
Nov 03, 2011 | Executive Sign Off |
Nov 03, 2011 | Sent to Photo Copy |
Nov 03, 2011 | Permit Approved |
Nov 23, 2011 | HPHC Historical Preservation No Effect |
Feb 06, 2012 | Land Evidence Date |